December 2011 (part 2)
Friday 2nd (cont)
Special machine tests for lack of movement in a north end concrete pile...
At south end, drilling continues within the casing...
Drill spins off the spoil
...and down-hole again
Drill spins off spoil again..
...most of it into the skip!
Digger and dumper truck clear the spoil away
Wed 7th Dec
<< Crane brings rebar for a borehole. ^ Some vital statistic is taken! ^
North end bore-holes filled with rebar and concrete, and linked by a concrete floor...
Crane moves more rebar for south end piles
Moving what seem to be trimmed-off sections of piles.
Sat 10th Dec
Week-end off
The five south end piles, with casings and now reburied