February 2012 (part 2)
Tuesday 7th
Crane unloads girders, scaffolding, connectors, etc, from a lorry.
The southern part of the lower causeway has been concreted, and scaffolding assembly has already begun there...
The north end of the lower causeway has been levelled and marked out for pits...
The purpose of all these components is to build the biggest mould for concrete seen on the bridge site yet!
Excavating behind north end...
Wed 8th Feb
Waterproof paint on new concrete
More north end excavation...
Harbour Office road - steelwork for concrete over sheet steel piling