February 2012 (part 1)
Thursday 2nd
The southern pillars bases have been covered over, and the lower causeway levelled off...
..but the small digger is making small depressions in carefully marked places...
The NE pillar base is partially covered, and the NW pillar steelwork is in place.
Sheet steel piling, Harbour Office road.
A work floor of concrete will be laid on the lower causeway - deeper concrete where the pits are will take the load of scaffolding uprights...
Curious visitors cast an eye on things!
The centre-line of the bridge-to-be
Lines of pits
Fri 3rd Feb
Mould has been assembled for NW pillar
Rocks and concrete pipe sections, stored near the Harbour Office
Earth moving work, behind the Harbour Office..
...where the new roadway from the bridge will be built
Southern part of lower causeway ready for concrete floor.
Building a work platform at the top of the mould..
Getting the steelwork dead centre within the mould...
Packing stuff away
Surveyor checks positions...
...at north end..
...and south end
Checking the concrete hopper
Final preparation of the mould