March 2012 (part 4)
Friday 16th (cont)
Crane (out of picture to the right) hoists a concrete hopper aloft...
Filling a hole at south end
Mon 19th Mar
Fitting the curved concrete side blocks begins.
Much fine adjustment is needed...
I didn't find out what these are!
Tue 20th Mar
The side blocks on the west are completed
Harbour Office road concrete finished for now..
Wed 21st Mar
Steelwork nearly complete...
A trench for utilities enters the worksite from the west
Steel pipes are threaded into the bridge steelwork from north end...
Meanwhile. more concrete has been poured by the sheet steel piling...
...and more steel work arrives on the bridge deck...
View from main road