March 2012 (part 1)
Thursday 1st
Bridge deck, east side: the sides of the bridge are made up of pre-cast, shaped, reinforced concrete blocks.
Upright girders for west side...
The concrete blocks on the east side are largely complete, but the west side uprights need more work before the blocks are added.
North end - concrete work
Harbour Office road - masons work on new stone wall, while further north more concreting takes place...
Between the new wall and the new concrete there's access to the shore.
Between the Harbour Office and the Swimming Pool, a concrete side block awaits use.
^ Side block at north end ^ >> Checking E side alignment >>
Fri 2nd Mar
Adding another block to the east side
The straight section of the west side blocks is completed
Fine adjustment of east side block
It's beginning to look like a bridge!
Delivery - more side blocks!
Detail of upright girders
North end - concrete side-foundations completed
Harbour Office road - new stone wall and shore access nearly complete
Unloading lorry...
Fine adjustment of a west side block...
..and another one
Preparing to extend floor to south end foundation block
Note the broom: mould must be kept clean and free of debris!