February 2012 (part 6)
Friday 24th (cont)
North end concrete job
Harbour Office road concrete job
Trenching, etc, behind Harbour Office
Bridge deck, from south end...
South end - forklift with floor panels
Sun 26th Feb
Wedges follow the curve at SW corner...
New foundation block stretches from north end.
Shuttering around steelwork against piling, north end
Hayle Harbour Office
Tue 28th Feb
Upright girders are fitted outside wedges, east side...
Masons' bags of granite blocks, for building a new stretch of stone wall, Harbour Office road.
Concreting along piles, north end
Upright girders fixed behind wedges...
Outside man fits girders, inside man fits trim to bottom of wedges.
Bottle screws hold the girders upright
Wed 29th Feb
South end - survey fixes the position of the marker beneath the theodolite
North end
Removing shuttering from concrete against steel pilings
Stonemasons building new wall, Harbour Office road...
Disc-cutter in action - water spray keeps granite dust down.
Little digger clearing old surface of Harbour Office road...
More shuttering, to extend the Harbour Office road reinforced concrete edge southwards.