January 2012 (part 3)
Thursday 19th (cont)
Lower causeway and pillar bases
North end - new shuttering
Two-part mould for reinforced concrete pillars
Harbour office road - reinforcing steel piles...
Checking below old road surface. (Harbour Office road will be resurfaced in March.)
Taking small compacting machine to south end...
Compacting trench infill
Another delivery of fill material
Using a small roller...
Fri 20th Jan
Rising tide flows through flume pipes, while water still drains from the higher part of Copperhouse Pool
Steelwork for southeast pillar in place
Pumping of pillar base continues...
Southwest pillar base
Preparing to add another base section...
Pillar steel work is held upright by two adjustable Acrow props.